Example page. Gregarious Simulation Systems and Project Relay are fictional; every figure is illustrative.
Week 12 client update
- Go-live forecast7 DecBaseline 30 Nov · +7 days
- Work done52%Up from 44% last week
- Budget spent$281.6k59% of $480k, $9.6k above plan to date
- Forecast at completion$497.6k+3.7% against the $480k budget
- Actions for GSS3All due by Wed 21 Oct, one decision
Seven changes since last Friday
- Overall status moved from green to amber.
- Integrations moved to amber: the billing test environment throttles our test runs. Risks →
- UAT start moved from 19 to 26 October. Schedule →
- Go-live forecast moved from 30 November to 7 December, unless GSS chooses option A. Options →
- Data migration work rose from 52% to 64% done; its reconciliation risk dropped from high to medium. Progress →
- Configuration complete moved from 16 to 21 October. Schedule →
- The SSO certificate risk closed, and two decisions were made. Decisions →
Changed figures are now highlighted across the page, with last week's value beside them.
The live page highlights what changed since last week, lets you compare the two go-live options and opens each risk for detail.
Summary and what we need from you
A good week on data and configuration, but the billing integration is behind and takes go-live with it unless we act by Wednesday.
- Data migration dry run 1 has now moved every customer account and 1.41 million tickets. Only 0.4% of those tickets fail reconciliation, all on malformed attachment names, and the fix is ready for dry run 2 on 23 October. Progress →
- The billing integration is about two weeks behind because its test environment caps how fast we can run tests. That pushes UAT to 26 October and go-live to 7 December. Schedule →
- We are $9.6k over plan to date from the extra integration work. The forecast at completion is $497.6k, 3.7% over budget, or $504.8k if we hold 30 November. Budget →
What we need from GSS
- Due Wed 21 Oct
Choose the go-live option
Hold 30 November with one more integration engineer, or move go-live to 7 December. Compare the options →
Owner: executive sponsor - Due Tue 20 Oct
Raise the billing test API limit
From 60 to 600 calls a minute for the test tenant, so integration tests can run in full.
Owner: GSS IT lead - Due Mon 19 Oct
Name 12 UAT testers
Ideally two per support queue, available for four half days from 26 October.
Owner: head of customer support
Decision needed: two ways to land go-live
Holding 30 November costs about $7.2k more, and buys five more working days of hypercare before the 18 December change freeze.
Pick an option and the go-live date, schedule, milestones and budget forecast on this page all follow it.Not possible in a PDF
In the live page, choosing an option redraws the schedule and the budget forecast.
Our recommendation is option A. Ten days of hypercare leaves no buffer if a billing issue appears in the first week, and the freeze would then hold any fix until January. Either way the scope does not change.
Schedule
Integrations push UAT a week later, and go-live with it, to 7 December.
| Milestone | Baseline | Forecast | Against baseline |
|---|
Progress
Work done rose from 44% to 52% this week, led by data migration and configuration.
| Workstream | Status | Done | Forecast end |
|---|
Every customer account and article is across; tickets are two thirds done
Budget
Spend is $9.6k ahead of plan, and the forecast lands $17.6k, or 3.7%, over the $480k budget.
- Budget$480.0kAgreed in the July statement of work
- Spent to date$281.6kPlan to date $272.0k
- Forecast at completion$497.6k+$17.6k against budget
Spend is $9.6k ahead of plan, more than half of it from the last two weeks of integration work
Risks and decisions
One new high risk this week, the billing test API limit, and GSS can close it by Tuesday.
Open risks
- Owner
- GSS IT lead
- Action
- Raise the limit to 600 calls a minute by Tue 20 Oct; we batch runs overnight until then
- If it slips
- Each extra week moves UAT and go-live by about a week
- Owner
- Our data lead
- Action
- Run the fix in dry run 2 on 23 Oct and report the result next Friday
- Owner
- Executive sponsor
- Action
- Choose the go-live option by Wed 21 Oct
- Owner
- Head of customer support
- Action
- Name the testers by Mon 19 Oct
Open a risk for its owner and action, or filter to what is new or what GSS owns.Not possible in a PDF
Closed this week: SSO certificate expiry in the test tenant, renewed by GSS IT on 14 October.
Decisions
- Migrate 24 months of ticket history; archive older tickets to read-only storage.Agreed by the GSS IT lead and our data lead. new
- Keep the legacy helpdesk read-only for 30 days after go-live.Agreed by the head of customer support. new
- Single sign-on for agents only; customers keep their email login.Agreed at the steering meeting.
Next week
Close configuration, run dry run 2 and get the UAT scripts to GSS for review.
- Rerun the full billing test suite once the API limit is raisedIntegrations lead
- Go-live option decided; we update this page the same dayGSS sponsor, James
- Sign off the last four support queues and close configurationConfiguration lead
- Send the UAT scripts to GSS for reviewTest lead
- Data migration dry run 2, with the attachment fixData lead
How this page was made
James wrote none of it by hand. He gave his AI three files and one instruction, and it published this page to SnapHost on the same link as last week.
- CSVrelay-tracker-export.csv
312 issues, 41 changed this week
RLY-188, Billing test API throttling, Integrations, Blocked RLY-203, Attachment rename on export, Data, In progress - MDclient-call-notes.md
Three calls with GSS, two decisions
Wed: keep legacy read-only 30 days (Head of Support) Thu: 24 months of history, archive the rest - XLSXtimesheet-week-12.xlsx
214 hours across six people
Integrations 71.5h Data 58.0h Config 44.0h
"Turn these into this week's client update for GSS: status, the schedule against baseline, budget, risks, decisions and what we need from them. Show what changed since last Friday, give them the two go-live options to compare, and publish it to the same SnapHost link as last week."
- Your AI builds the pageFrom the files you already have: tracker, notes, timesheet.
- SnapHost publishes itStraight from your AI, as a private, hosted, live page.
- Only your client sees itThe people you name verify their email; nobody else gets in.
- Next Friday, same linkPublish again and the page updates in place; nothing to resend.
Build and share your own client update with SnapHost
You built something with AI. snaphost.ai is the fastest way to put it in front of someone, live, and only for the people you choose.
Definitions
How the status colours, progress and forecasts on this page are worked out.
- Green, amber, red
- Green: on plan. Amber: a milestone or cost is at risk and we have a recovery plan. Red: a milestone will be missed without a decision from GSS.
- Work done
- Each workstream's progress weighted by its share of the budget.
- Baseline
- The plan agreed at the end of discovery on 4 September.
- Forecast at completion
- Spend to date plus the cost of the remaining work at agreed rates, for the go-live plan selected.
- Hypercare
- Extra support from the project team after go-live, until the change freeze on 18 December.
Gregarious Simulation Systems, Project Relay and every name, date and figure on this page are fictional. This is an example made with SnapHost to show what an AI made client update can look like.